Project pipeline
Growth
Kumba Iron Ore has developed an exciting project pipeline of new
opportunities and intends to grow its total production capacity to more
than 70 Mtpa by 2015, which will be more than double its current
capacity. The group will exploit the full potential of the substantial
Northern Cape iron ore resources under its control, and it has access to
other opportunities in West Africa.
Kumba Iron Ore is dependent on the expansion of the Sishen-Saldanha
export channel as well as off-take agreements from domestic steel
producers to realise some of the South African opportunities. It is,
therefore, engaged in an active programme of securing cooperation
and participation from the parties involved.
Sishen Expansion Project
In February 2005, the board of Kumba Resources approved an amount
of R3 605 million for the development of the SEP1 with a rated
production capacity of 10 Mtpa. The Kumba Resources board approved
a further R1 495 million to expand the production capacity of the SEP1
by an additional 3 Mtpa to a total of 13 Mtpa.
The SEP1 project utilises jig technology to extract additional saleable
product from 21 Mtpa of feedstock – about 8 Mt that was previously
regarded as waste and 13 Mt of which will be new ROM material. The
final product will have an average iron content of 64 percent compared
with the 66 percent iron content of the current Sishen product, and
will be marketed to a range of existing and new clients.
The construction phase of the project is nearing completion and
production is scheduled to begin in the second half of 2007 with
full ramp-up to nameplate capacity by early 2009.
Export Logistics Expansion Project
Kumba Iron Ore and Transnet concluded an agreement to expand
the Sishen-Saldanha export channel in February 2005, increasing the
group’s contractual iron ore rail allocation on the channel to 35 Mtpa.
This capacity will be reached in 2009 and overall development is
aligned with the expansion of Kumba Iron Ore’s production capacity
at Sishen Mine.
Transnet has embarked on a further study to increase the channel’s
capacity from 47 Mtpa to 67 Mtpa. Kumba Iron Ore intends finalising
its studies on the Sishen South Project and further expansions at
Sishen Mine to coincide with the completion of the Transnet study by
mid-2007. This will place Kumba Iron Ore in a position to commit to further expansion of its contractual rail allocation on the Sishen-
Saldanha export channel.
Sishen South Project
This project involves the development of a greenfield open-cast
operation on a group of iron ore bodies situated some 80 km south
of Sishen Mine, and immediately to the west of the current mining
operations of Assmang’s Beeshoek Iron Ore mine.
Due to export logistics constraints, a phased approach for developing
the mine was envisaged, but the first phase development of 3 Mtpa
did not meet Kumba Iron Ore’s requirements in respect of capital
investment and railway logistics. A feasibility study for the development
of a 9 Mtpa operation is currently in progress and will be completed by
mid-2007. A range of products similar to the Sishen Expansion Project
will be produced. An investment decision is expected during 2007. The
decision depends on the outcome of Transnet’s feasibility study for the
essential logistics expansions. A study is also under way on further
expansion of the Sishen South Mine that will include the installation
of a beneficiation plant.
Under certain circumstances, Mittal may have the right to participate in
and appropriately fund future SIOC iron ore expansion projects or new
projects in South Africa. Kumba Iron Ore has previously indicated that
there was a difference in interpretation with regards to the terms of
this agreement with Mittal. Regrettably these differences could not be
resolved amicably and the parties have now decided to resort to
arbitration.
Phoenix Project
The objective of the Phoenix Project is to extend Thabazimbi Mine’s
current LOM from four to thirty years. Thabazimbi Mine has a captive
supply agreement with Mittal and currently produces some 2,4 Mtpa
of lump and fine ore for Mittal.
The extended LOM will be achieved by exploiting the medium grade in
situ banded ironstone formation, which, when combined with highgrade
hematite, provides an economically viable iron ore feed. Based
on test work and technology similar to the Sishen Expansion Project, a
flow sheet has been developed to produce the required tonnages and
qualities of lump and fine ore products. The project is currently in the
feasibility phase, which will be completed in the second quarter of
2007. Kumba Iron Ore has embarked on a rigorous value engineering
exercise as part of the feasibility study to review and reduce capital and
operating cost estimates for the project.
Mittal has given notice that it does not wish to participate in the project,
but has requested that Kumba Iron Ore complete the feasibility study. In
light of this decision alternative uses for the iron ore are currently under
investigation by the company.
Falémé Project
Miferso, a Senegalese state-controlled company, owns the exploration
rights to the Falémé iron ore resources located in the southeastern
corner of Senegal. Kumba Iron Ore (through Kumba International B.V.)
and Miferso concluded an agreement in July 2004 for, amongst other
things, the exploration of the resources with a view to creating and
operating an export-orientated iron ore mine at Falémé.
Kumba Iron Ore exercised its option to acquire a 80 percent interest in
the project in November 2005. Following receipt of notice of such
exercise, the government of Senegal and Miferso informed Kumba Iron
Ore that they disputed the validity of such right and that the
Government of Senegal had concluded an agreement with Mittal Steel
for the development of the Falémé project.
Sishen Expansion Project II
Further utilisation of the medium and low grade resources at Sishen is
currently being examined in a business case study due for completion
in June 2007. The study focuses specifically on the development of an
optimised Whittle pit shell for Sishen Mine incorporating the use of
lower grade resources, and the definition of an optimised product
strategy for marketing these products as well as the existing range
of products produced at the mine.
The study considers additional production capacity of between 10 and
20 Mtpa and a final decision on production capacity will depend on
the eventual expansion potential of the Sishen-Saldanha export
channel, domestic growth in demand and the results of the export
marketing study.
The project will use technology similar to that developed for the SEP1
and production from this facility could start by 2011.
Zandrivierspoort Project
The former Kumba Resources acquired a 50 percent interest in the
PIC in the 1980s and has conducted extensive exploration and
technical studies to develop the project. This company owns the
surface rights for the Zandrivierspoort iron ore project, 30 km north of
Polokwane. Phelps Dodge sold its 50 percent interest in PIC to Mittal
Steel in December 2004. Since then, the parties have developed a
framework for a pre-feasibility study, commenced with exploration
activities in 2005 and are progressing to the evaluation of alternative
processing and final product options in 2007. The parties intend to
commit to a detailed bankable feasibility study in 2008, if interim
studies prove a robust and viable business case.
|