Production report for the six months ended 30 June 2009

Production summary

Total iron ore production increased by 11% in the second quarter from a year earlier to 9,82Mt. This was due mainly to the additional production delivered by the jig plant and stable performance from the DMS plant.

Six month overview

     Year to date      
  30 June   30 June   %  
‘000 tonnes 2009   2008   change  
Iron ore 19 147   17 063   12  
– Lump 11 671   10 180   15  
– Fines 7 476   6 883   9  
Mine production 19 147   17 063   12  
– Sishen Mine 18 032   15 788   14  
   DMS plant 13 617   13 998   (3)  
   Jig plant 4 415   1 292   242  
   Other -   498   -  
– Thabazimbi Mine 1 115   1 275   (13)  

Quarterly overview

     Quarter ended          Quarter ended      
  30 June   30 June   %   31 March   31 March   %  
‘000 tonnes 2009   2008   change   2009   2008   change  
Iron ore 9 824   8 873   11   9 323   8 190   14  
– Lump 6 076   5 292   15   5 595   4 888   14  
– Fines 3 748   3 581   5   3 728   3 302   13  
Mine production 9 824   8 873   11   9 323   8 190   14  
– Sishen Mine 9 339   8 247   13   8 693   7 541   15  
   DMS plant 6 964   6 841   2   6 653   7 157   (7)  
   Jig plant 2 375   908   162   2 040   384   431  
   Other   498          
– Thabazimbi Mine 485   626   (23)   630   649   (3)